House Update - February 7, 2008
They are nearing completion on the framing. The rafters are 97.2% done and the roof is scheduled to be decked on Monday (Feb. 11) as long as the wind cooperates. Lately, it has been very windy making it difficult to work on the roof. The windows and doors will be installed on Friday (Feb. 8).

Front of House